Most complex technological stage has been completed at Eastern exit from Ufa

At the Eastern exit from Ufa, underground tunneling work has been completed, the Head of Bashkiria said on his social media.

“It was the most voluminous and technologically complex stage. Further, until June, the builders will be constructing permanent structures. Currently, the upper, lower, and side parts are assembled in the southern tunnel, the foundation is being concreted under the road surface, and engineering networks are being laid in the northern tunnel. In general, the Eastern exit is almost 63% ready. The schedule is observed. The work schedule is 24/7,” said Radiy Khabirov.

As Bashinform News Agency reported, a month ago, the construction of a road maintenance enterprise began at the site. The completion date for the Eastern Exit is the end of 2023.