It is planned to direct 6.8 billion rubles for Zatonskaya CHP construction completion
UFA, 24 November 2014. /Bashinform News Agency, Rozaliya Valeeva/. It is planned to direct 6.8 billion rubles to perform works on completion of the combined cycle gas turbine with capacity of 440 MW at Zatonskaya CHP in Ufa district.
LLC "Inter RAO - Procurement Centre" announced a launch of competitive negotiations.
Bids will be accepted until December 8, the results will be announced on December 19, 2014.
Works are expected to be completed by April 2017.
Earlier it was reported that the construction project of combined cycle gas turbine at Zatonskaya CHP will be rendered state support in the form of preferential taxation. This decision was made by the Governmental Commission for consideration and support of priority investment projects in Bashkortostan. Total investment in the construction of gas turbine at Zatonskaya CHP exceeds 21 billion rubles. The project initiator is LLC "Bashkir Generation Company".